Hinkley cost overruns a warning for future projects

  • Published
Hinkley PointImage source, Reuters

As recently as July, EDF assured the BBC that Hinkley Point C was proceeding on budget and on schedule.

I'm told that today's announcement that costs could overrun by up to £2.9bn was as a result of a review conducted after the "big concrete pour".

It seems that despite the assurances that lessons had been learnt at Flamanville, in France, and Olkiluoto, in Finland, (both of which have overrun by many years and many billions), it is almost impossible to be accurate about cost and timescale when it comes to nuclear power.

To be clear, these cost overruns will not hit UK consumers. One of the reasons the price agreed for the electricity it will one day produce was so high (£92.50 per megawatt hour at a time when the wholesale market price was around £40) was that EDF agreed to absorb any budget-busting delays.

However, a new way of paying for further nuclear stations, such as Sizewell, is being considered. Under this new model (Regulated Asset Base), consumers would see costs of construction added to their bills as the project went along. This is a way of reducing the cost as you don't have to raise all the finance up front. However, it means that customers could be exposed to cost overruns.

Government's big call

That is why today's announcement is important and why EDF will find it harder to make the argument for building Sizewell.

That argument is already getting tougher as the price of zero carbon offshore wind continues to plummet. The last auction saw prices below £40 per megawatt hour - the lowest estimate for the Sizewell energy price I've heard is £60.

EDF correctly points out that renewables are intermittent - the wind doesn't always blow and the sun doesn't always shine. But we are moving towards a future in which electricity storage issues are being addressed - eg, using electric cars to double as home batteries, using renewable to creates hydrogen which can be stored and burned with only water as a by product.

We will need a lot of electricity in the future as we decarbonise transport and heating - and nuclear may well have a role in producing low carbon energy at scale.

But with technology moving fast, making a 40-year bet on another nuclear station with a history of cost and schedule overruns, coupled with a funding model that exposes consumers to those overruns, is a big call for any government to make.