New nuclear plant at Sizewell set for green light

  • Published
Sizewell A, B and C modelImage source, EDF
Image caption,

EDF says Sizewell C will provide electricity for six million homes and create 25,000 jobs

The government is close to giving the green light to a new nuclear power station at Sizewell in Suffolk.

The BBC has learned that talks with the Sizewell contractor, EDF, have intensified in recent weeks.

This comes after projects in Anglesey and Cumbria have suffered major setbacks when Japanese firms Hitachi and Toshiba pulled out.

Government officials are insisting that it "remains committed to new nuclear".

Although final approval is subject to a planning process, the final decision rests with the Secretary of State for Business Energy and Industrial Strategy.

This commitment to new nuclear may be included as part of a 10-point government plan to be published in early November.

That plan is expected ahead of a detailed government white paper in late November which will attempt to set out the course of UK energy policy for decades to come.

Unions have warned that a failure to transfer jobs, skills and new opportunities from the current project under construction at Hinkley Point in Somerset to Sizewell in Suffolk would put thousands of high skilled jobs at risk.

The details of how new reactors at Sizewell will be paid for are still being hammered out.

The government is considering taking an ownership stake and consumers may see a small addition to their bills to pay for the project as it is being built, in order to drive down the costs of financing a project that may cost up to £20bn and take about 10 years to build.

The bigger the government stake, the smaller the call on consumers to "pay as you go" for the development and construction costs.

This funding model has been treated with suspicion before, as opponents say it transfers the risk of delays and budget overruns from the contractor to the consumer and the taxpayer.

However, the BBC understands that the fact Sizewell C is a carbon copy of Hinkley - which has seen work on a second reactor there completed 30% more quickly than the first - is thought to have substantially mitigated that risk.

One of the reasons that the electricity that Hinkley will one day produce is so expensive (£92.50 per megawatt hour, compared with gas and wind at about £40) is that the constructors were required to shoulder the risk of any cost overruns themselves. EDF estimates that the cost of electricity produced at Sizewell will be somewhere between £40 and £60.

The government hopes that the regular payments from both the government and consumers will encourage private sector investors like pension funds to also take an ownership stake in the project.

Image source, Getty Images
Image caption,

Hitachi scrapped plans for a £20bn nuclear plant at Wylfa last month

There are three reasons that Sizewell C is expected to get government blessing:

1 - Government policy

The government has recently confirmed that it "remains committed to new nuclear" as part of a mix of low-carbon electricity production. At the moment, Sizewell C is realistically the only horse in the race.

Of the original six sites earmarked a decade ago for a new fleet of nuclear reactors, three (Wylfa, Moorside and Oldbury) have seen contractors pull out, with only one already under construction at Hinkley Point in Somerset.

Plans for Small Modular Reactors (SMRs) have attracted interest and research investment from the government, but are thought to be many years from being a realistic alternative to big nuclear plants. Rolls Royce, which is spearheading this research and development, may disagree, but as one industry source put it, "I don't think that anyone really thinks that SMRs are a thing just yet."

That means Sizewell C is the only realistic option left on the table.

2 - Hitting net zero

Even some of the most prominent evangelists for renewables such as wind and solar privately admit that you can't get to net zero by renewables alone without compromising the stability of the electricity grid.

There are times when the wind doesn't blow and the sun doesn't shine. It is possible to develop enhanced battery storage and use "smart grid" technology to flick between different renewable sources, but to do that would require billions of investment in a radical redesign of the national grid to provide that kind of flexibility and connectivity.

Nuclear currently supplies more than 20% of all UK electricity and although offshore wind can be expanded enormously, keeping pace with the soaring demand expected for electricity in our transport and heating systems would be asking too much of renewables.

We will need gigantic quantities of low-carbon electricity and when it's built and running, that's what nuclear gives you. The new plants at Hinkley and Sizewell alone are expected to supply 14% of the UK's electricity needs.

3 - Jobs, jobs, jobs

A decision to green-light Sizewell will be welcomed by unions as an important move to preserve jobs and expertise in a high-skilled and well-paid sector.

The union Unite has called on the government to approve the plans, arguing that 10,000 jobs are "in the balance" if the project does not go ahead.

The government recognises this.

Energy industry sources agreed, telling the BBC that there is a "compelling industrial case" for the "lift and shift" of jobs and skills from the plant currently under construction at Hinkley Point in Somerset to Sizewell in Suffolk.

Contractors EDF claim Sizewell will create and support 70,000 direct and indirect jobs throughout the UK.

But there are also problems:

China

Chinese state-owned company CGN already owns a 33% stake in Hinkley Point C in Somerset, currently under construction by French firm EDF, which owns the other two-thirds.

The Chinese firm also took a 20% stake in the development phase of Sizewell on the understanding it would participate in the construction phase and then land the ultimate prize of building a reactor of its own design at Bradwell in Essex.

Sources within government and the industry say Chinese involvement in designing and running its own design nuclear reactor on UK soil "looks dead", given revived security concerns and deteriorating diplomatic relations after the government's decision to phase out Chinese firm Huawei's equipment from a new generation of telecommunication networks.

If a mobile network is considered too sensitive, it's hard to argue that a nuclear power station is not. Sources close to CGN say the company recognises the new political realities, but still hopes to be able to be an "arm's-length suppler" to the project, having built a similar plant in Taishan which is already up and running.

Local opinion

Local opinion in Suffolk is mixed. Some residents of the surrounding picturesque and well-heeled villages fear a future of HGVs thundering down country lanes and have mounted campaigns to stop the project.

Others point to the benefits of the many thousands of jobs the project will create in an area that also includes some of the UK's most deprived areas. One Stop Sizewell poster had "Jobs not Snobs" written over it.

Technology of the past

Opponents of Sizewell say that big nuclear is a technology of the past. The future lies with a rapid expansion of renewables, along with the development of large-scale battery technology and technology that optimises the supply and demand of energy in real time.

The chairman of Together Against Sizewell C, Pete Wilkinson, argues that "renewables out-compete nuclear on every front - cost, waste, jobs, CO2 and time for deployment".

Why nuclear?

Decarbonising our electricity supply is crucial if the UK is to meet its net zero target by 2050.

But at the moment there aren't many choices when it comes to low carbon energy.

The UK isn't a great location for solar power. We don't have much sun, or much land.

Wind, particularly offshore wind, is a much better bet. Boris Johnson has said he expects offshore wind to be able to generate 40GW for the UK by 2030 - more than half current electricity demand.

However, that's already an ambitious target and it is hard to see how the industry could be developed more rapidly than that.

And you've also got the question of what to do when the wind doesn't blow and the sun doesn't shine.

Battery and other energy storage technologies are developing rapidly but are expensive.

Meanwhile, other more dependable low carbon technologies - carbon capture and storage, geothermal, wave and tidal power etc - may be promising but are not yet available at scale.

Leaving nuclear power pretty much the only remaining low carbon option.

Not either/or

One of the UK's leading energy experts, Prof Dieter Helm, says some of the numbers on cost are misleading, as basic comparisons underestimate the cost of intermittency (when the wind doesn't blow and the sun doesn't shine) and the necessary changes to the overall design of the energy grid to accommodate the large number of turbines and solar farms you would need to replace the constant flow (baseload) of energy you get from nuclear power.

"No one thinks nuclear can solve the problem, but it's also hard to see how wind gets you there either and in fact neither of them claim that to be the case. One thing is certain, the government has to stop dithering and start putting some stakes in the ground," he says.

Ultimately, for the government, it is neither desirable nor necessary for this to be an either/or decision. The Committee on Climate Change (CCC) has said the road to net zero will require a combination of technologies.

It will also cost a lot of money which, one way or another, will be paid by consumers and taxpayers.

Decarbonising the electricity supply is the relatively easy bit. Decarbonising industrial processes and the way we heat our homes is the hard bit. There are 25 million gas boilers in our homes which will need replacing, for a start.

The CCC estimates the cost of getting to net zero by 2050 at a TRILLION pounds. That means spending £30bn a year - every year - for the next 30 years. That's roughly 1.5% of UK GDP. Put that way, it sounds possible but is still a very, very formidable target.