More remedial works for problem Cowes chain ferry
- Published
A chain ferry on the Isle of Wight which has been beset with problems is to undergo further remedial work - this time to tackle noise and vibration.
Since launching in May 2017, Floating Bridge Number 6 has run aground, broken down and remains unable to operate during certain tidal conditions.
In the latest attempts to resolve the problems, the slipway at Cowes will be fitted with matting.
A "shoe" will also be fitted to the end of the vessel's ramp next week.
The £3.2m vessel, which links Cowes with East Cowes, will be out of service on Tuesday evening from 19:00 to 23:30 BST while the matting is fitted and again for the shoe fitting which will provide a flat landing point for the ramp.
Isle of Wight Council leader Dave Stewart said the authority remained "determined to make the necessary improvements to the floating bridge".
Soon after the ferry's launch in May 2017, car bumpers were scraped as vehicles disembarked and it suffered an electrical fault on its second day.
It has been in and out of service due to problems including night-time noise, running aground and a broken prow chain.
Currently, the vessel cannot run during a fast-flowing spring ebb tide due to the depth of the chain - which poses a risk to other vessels.
Local shipbuilder, Wight Shipyard, has been brought in to try and rectify some of the problems.
The journey by road from Cowes to East Cowes is about 10 miles (16km).
Floating bridge timeline:
13 May 2017 - Vessel launched
14 May - Broke down
15 May - Service suspended by Maritime and Coastguard Agency
7 June - Ran aground
9 June - Ran aground for a second time
9 June - Council said it had cleared "silt build-up that caused the floating bridge to ground"
10 June - Ran aground a third time
13 June to 3 July - Taken out of service at low tide
30 June - Broke down due to electrical fault
21 July - Withdrawn from service at night due to noise levels
4 September - Withdrawn from service indefinitely
11 December - Service resumed as part of extended trial
2 February 2018 - Broken prow chain
14 April - Ran aground
15-16 July - Out of service for "improvements"
Ongoing - Unable to run during low tides
8 August - Ran aground
9-10 August - Out of service due to problem with prow hinge
4 September - Out of service for slipway remedial works
- Published10 August 2018
- Published19 July 2018
- Published16 April 2018
- Published5 April 2018
- Published7 February 2018
- Published3 February 2018
- Published30 December 2017
- Published7 December 2017
- Published26 October 2017
- Published21 September 2017
- Published31 August 2017