Aquind interconnector: MoD has 'serious' concerns over plan

  • Published
Claire CoutinhoImage source, Reuters
Image caption,

Energy secretary Claire Coutinho is due to make a final decision on the £1.2bn electricity link

The Ministry of Defence (MoD) has "serious national security concerns" over a proposed electricity link between England and France.

Aquind Ltd wants to lay cables through Portsmouth, Hampshire, to Normandy.

The MoD submitted a letter to the planning inspectorate after a delay in the project's planning decision was announced in January.

An Aquind spokesperson said the company was "keen" to address the concerns "in good faith".

The verdict now rests with Claire Coutinho, the secretary of state of energy security and net zero.

In its letter, the MoD stressed the need for further collaboration with the Department for Energy Security and Net Zero to address its concerns in a manner consistent with their "sensitive nature".

Image source, Paul Gonella
Image caption,

The project has attracted local protests

It asked the government department to clarify the proposed process and allow both the MoD and Aquind to provide feedback, along with a six-week extension to prepare representations.

The MoD expressed reluctance to engage with Aquind recently due to the absence of an agreed process "which affords appropriate protection to MoD's concerns".

It added that it would keep this situation "under review" as it develops its evidence.

Aquind is part-owned by Russian-born former oil executive Victor Fedotov.

In October 2021, the BBC's Panorama programme revealed how some of Mr Fedotov's other companies, which made donations to Conservative MPs, had profited from a pipeline deal in Russia.

Image source, Chris Illingworth
Image caption,

The interconnector would make landfall at Eastney beach in Portsmouth

In 2023, the government's decision to refuse permission for the £1.2bn link was overturned in the High Court.

Aquind spokesperson Ben Iorio said it was disappointing that the "alleged concerns" were not outlined.

He said: "The manner of the MoD's last-minute interference will have negative impacts on all proposed developments and marine users in and around Portsmouth, including renewable energy, interconnectors, fisheries and many others."

He added that the company "remain ready and willing" to address the MoD's planning-related questions.

This article was updated on 26 March 2024 to make it clear Panorama revealed how some of Mr Fedotov's companies had profited from a pipeline deal in Russia, rather than revealing his part ownership of Aquind, which was reported by The Times in 2020, external.

Follow BBC South on Facebook, external, X, external, or Instagram, external. Send your story ideas to south.newsonline@bbc.co.uk or via WhatsApp on 0808 100 2240, external.

Related internet links

The BBC is not responsible for the content of external sites.