Elizabeth line: Final stage to be completed with increase in peak services
- Published
The "final milestone" of the Elizabeth line is set to be completed next month, with trains into central London during peak times being increased.
Transport for London (TfL) said a train would run roughly every two-and-a-half minutes between Paddington and Whitechapel at peak times.
Passengers travelling between Shenfield in Essex, and east London will now be able to travel direct to Heathrow Airport without having to change.
The new timetable will run from 21 May.
Three days later will mark the one year anniversary of the line officially opening across London.
TfL says more than 140 million customer journeys have taken place so far, averaging at about 600,000 journeys being made each weekday.
Other changes include:
More trains running between Canary Wharf and Abbey Wood in the peak
More peak time services between Gidea Park and Liverpool Street National Rail Station, providing a faster route for those exiting to Bishopsgate
In the west, there will be more peak services from Reading
Six services per hour will head to Heathrow Airport; all trains will stop at terminals 2 and 3, with four per hour continuing to Terminal 4, and two per hour continuing to Terminal 5.
The Mayor of London, Sadiq Khan, said: "Delivering the Elizabeth line has been transformational for our city, with hundreds of thousands of Londoners and visitors now enjoying the fast and reliable trains each day.
"The introduction of the final timetable next month marks the last milestone of the Crossrail project and will enable the Elizabeth line to provide even more frequent, speedier journeys and better connect the capital."
Follow BBC London on Facebook, external, Twitter , externaland Instagram, external. Send your story ideas to hellobbclondon@bbc.co.uk, external
- Published1 February 2023
- Published25 January 2023
- Published20 December 2022
- Published28 September 2022
- Published30 May 2022
- Published24 May 2022
- Published24 May 2022
- Published24 May 2022