Work begins to protect Blue Anchor coastal homes from sea

  • Published
A large pile of rocks on a beachImage source, Cara Strom
Image caption,

The £3.7m project will boost sea defences at Blue Anchor Bay

Work is underway to protect a coastal road and nearby homes from sea erosion.

More than 13,500 tonnes (13.5 million kg) of rock are arriving in Blue Anchor, near Minehead in Somerset.

The coastline has seen significant erosion and the B3191 has been closed at the Watchet end since mid-January.

The £3.8m scheme aims to provide permanent support to the walls and mudstone cliff, as well as a section of the road.

Rock delivery from Glensanda Quarry in western Scotland is expected to take 32 days.

Image source, Somerset Council
Image caption,

Rocks are being delivered to the beach by a barge

The rock will be transferred onto a barge and deposited on the beach during high tide, subject to suitable weather. It will then be moved up the beach at low tide.

Access to the beach may be restricted at times and members of the public are asked to stay clear of rock piles.

Once all of the rock has been delivered and placed, the upper slope of the cliff will be reprofiled, with the work expected to be finished by the end of September.

Image source, Somerset Council
Image caption,

Rock delivery from western Scotland is expected to take 32 days

Councillor Sarah Dyke, lead member for environment and climate change at Somerset Council, said: "I am delighted to see these important works finally take place, benefiting the communities in west Somerset.

"The scheme will provide a more permanent defence against coastal erosion."