Final 'abnormal load' through Ipswich reaches its destination
- Published

The load manoeuvred its final turn into Eye airfield
A third and final "abnormal load" has managed to squeeze its way through the streets of Ipswich to its destination - a new power station in Eye.
The transformer was the smallest of three loads that have recently been unloaded from Ipswich docks.
The journey began at about 05:30 GMT and inched its way through the town until it reached Hill View Business Park in Claydon, at about 14:30.
It then travelled on to its final destination via rolling roadblocks.
Suffolk Highways thanked all the teams involved in a social media post on X, external, who worked over four Sundays to get the equipment to Eye.

It gently navigated the Felixstowe Road and Derby Road junction
The transformer will form part of the Progress Power Station.
It travelled along the same route as loads one and two, including Cliff Road, Duke Street, Fore Street, Bishops Hill, Felixstowe Road, Derby Road, Tomline Road, Foxhall Road, Grove Lane and on to St Helen's Street.
It also went along St Margaret's Street, Crown Street, St Matthew's Street and on to Norwich Road.

Traffic signals were removed on Crown Street to allow the abnormal load to pass over
The second part of the journey saw rolling road closures installed along the A14 and A140.
Suffolk Highways said: "A huge thank you and well done to all teams involved.
"Three abnormal loads moved, a transformer, turbine and a generator, all moved in four Sundays."

A temporary bridge was made at Brockford Street for the load to pass over

Follow East of England news on Facebook, external, Instagram, external and X, external. Got a story? Email eastofenglandnews@bbc.co.uk , externalor WhatsApp 0800 169 183
- Published5 November 2023
- Published29 October 2023
- Published22 October 2023
- Published20 September 2023