DG One leisure centre inquiry findings due
- Published
The findings of an independent inquiry into the construction failings at a flagship leisure centre in southern Scotland are set to be revealed.
The investigation into the issues at the DG One complex in Dumfries has cost just under £250,000.
Prof John Cole, who carried out the inquiry, is set to address Dumfries and Galloway Council next week.
He was given a wide-ranging remit to look at the leadership and management of the building project.
The council-run facility - which initially cost £17m to build - was shut three-and-a-half years ago for major repairs.
A compensation deal to cover remedial works which were estimated at about £10m at the time was agreed with original contractors Keir Northern.
However, the emergence of previously undiscovered problems has seen those costs rise to £19.3m.
Prof Cole's inquiry is expected to look at why major structural issues at the site were not picked up sooner.