New Manx ferry terminal in Liverpool 'on schedule' for spring opening

  • Published
New ferry terminal in LiverpoolImage source, IOM GOV
Image caption,

The cost of the project has spiralled to more than £70m

A new ferry terminal in Liverpool is "on schedule" to start operations this spring, the Isle of Man Steam Packet Company has said.

Use of the facilities will only begin once berth fit and mooring trials have been completed, the firm said.

The cost of the Manx government-funded scheme at Princes Half Tide Dock has doubled to more than £70m and has been beset by delays.

Contingency plans are in place to continue to use the Pier Head.

The high speed Manannan's seasonal sailings between Douglas and Liverpool are set to begin at the end of March, and the vessel is to be given priority in carrying out mooring trials.

New flagship vessel Manxman's first trip to the new landing stage is scheduled for November.

Image source, IOM GOV
Image caption,

Mooring trials are due to be carried out with all the Steam Packet vessels

Managing director Brian Thompson said while the firm was "excited about the prospect of improved passenger experience", taking a vessel to a new berth for the first time was an "involved process" and safety was the "top priority".

He said: "All being well, we are on schedule to commence operations from the new Isle of Man Government terminal in Spring 2024, but until the berth fit has taken place and we've started berth trials we won't be in a position to commit to a firm date for the first sailing.

Work still to be completed at the site includes the installation of quay wall fenders and a landside fuel tank.