Eastleigh derailed train: Limited services resume

  • Published
Derailment
Image caption,

Six wagons came off the track at Eastleigh on Tuesday

Rail services have resumed almost a week after a freight train derailed.

Six 52-tonne wagons came off the track at Eastleigh on Tuesday - blocking the line between Southampton and Basingstoke - and damaging points equipment.

Temporary track has allowed services to resume but passengers for Eastleigh still face further diversions.

Network Rail said the derailment had caused "significant damage".

CrossCountry, SWR and Southern routes were affected by the disruption, with buses replacing cancelled services and routes diverted.

After the Freightliner wagons were cleared on Thursday, a 520ft (160m) stretch of temporary track was installed to allow trains to run while a full repair is carried out.

John Halsall, of Network Rail, said: "It has been an incredibly complex job and has taken much longer than we initially expected.

"The sheer weight of these trains coming off the rails and on to the tracks has caused significant damage to the infrastructure, including the track, and signalling equipment - not just the lights but the cabling and power."

This Twitter post cannot be displayed in your browser. Please enable Javascript or try a different browser.View original content on Twitter
The BBC is not responsible for the content of external sites.
Skip twitter post by Network Rail Wessex

Allow Twitter content?

This article contains content provided by Twitter. We ask for your permission before anything is loaded, as they may be using cookies and other technologies. You may want to read Twitter’s cookie policy, external and privacy policy, external before accepting. To view this content choose ‘accept and continue’.

The BBC is not responsible for the content of external sites.
End of twitter post by Network Rail Wessex

South Western Railway said trains running on the main line from Winchester to Southampton would be unable to stop at Eastleigh for several weeks while the new track is designed and constructed.

A Rail Accident Investigation Branch report is expected to take several months to complete.

Image caption,

Specialist lifting equipment was brought in to move the stricken freight train carriages

Image caption,

The derailment damaged points equipment