Lowestoft third crossing: Recommended option criticised by Peter Colby

  • Published
LowestoftImage source, Mike page
Image caption,

Lake Lothing (photographed looking west) is crossed by the Bascule Bridge at the harbour end

A study has revealed the preferred £95m option for a third waterway crossing in Lowestoft, but a local businessman says his proposal would be cheaper.

Suffolk County Council commissioned independent engineers WSP to produce a report, external last year.

WSP has favoured a four-lane lifting bridge to the west of the existing Bascule Bridge.

Peter Colby, a local businessman, claimed his barrage bridge, external proposal would cost £65m.

WSP looked at a western, central or eastern crossing of Lake Lothing and recommended an eastern crossing linking Belvedere Road to Denmark Road via Commercial Road and a new bridge over the railway.

Image source, WSP
Image caption,

WSP considered crossings in western, central and eastern locations across Lake Lothing

WSP's Lowestoft third crossing options and costs

  • Western bridge - from Waveney Drive to Peto Way, not costed by WSP due to "lack of support"

  • Central bridge - from Waveney Drive/A12 roundabout to Commercial Road with railway bridge, £116.5m

  • Eastern bridge - from Belvedere Road to Denmark Road with railway bridge, £95m

Peter Aldous, Conservative MP for Waveney, said it was a "significant step forward" in dealing with road congestion around the Bascule Bridge.

"Most importantly it will not have a negative impact on the port, which supports 1,100 jobs and provides about £79m to the economy per annum," he said.

Image source, WSP
Image caption,

WSP's refined option for the eastern location crosses the water next to the existing Bascule Bridge

Peter Colby, Lowestoft businessman and commercial property developer, said his central location proposal for a Dutch-style barrage crossing linking the Waveney Drive/A12 roundabout with Rotterdam Road would only cost £65m.

He said: "I don't believe [the WSP preferred option] is the right crossing or that they've really considered the barrage crossing.

"The port is not very busy and one could say it's run-down - and the central crossing option is well clear of the turning circle [for boats]."

Image source, Peter Colby
Image caption,

Peter Colby's barrage design was similar to this one in The Netherlands

Image source, Andrew Woodger
Image caption,

Peter Colby's design for a barrage would involve damming the lake and having a lock

The WSP report said a bridge at the central location would cost £116.5m and Mr Colby's barrage scheme had "disadvantages... particularly in respect of the harbour operations and associated impacts on potential incoming future investment in the town".

Mark Bee, Conservative leader of Suffolk County Council, said: "We've got to come up with a project that's going to work and tick the boxes as far as releasing government funding is concerned.

"There is no point in putting forward something that doesn't do the job it's got to do and messes up the port."

Mr Bee said the county council and Waveney District Council would now consider the report fully before putting a detailed case for funding to the government.

Related internet links

The BBC is not responsible for the content of external sites.