Orwell Bridge photographed during abseiling survey
- Published
![Picture looks up at the bridge close to one of the huge concrete pillars holding it up.](https://ichef.bbci.co.uk/ace/standard/976/cpsprodpb/75A7/production/_131291103_bridge1.jpg)
The bridge is 43m (141ft) tall, and rests on pilings 40m (131ft) deep into the river bed
A well-known landmark bridge has been photographed from different angles as part of an abseiling survey carried out by contractors.
The 41-year-old structure, on the outskirts of Ipswich, has had a midlife health check to inspect the condition of the concrete.
![Worker is suspended under the carriageway of the bridge, above the ground.](https://ichef.bbci.co.uk/ace/standard/976/cpsprodpb/4AAF/production/_131291191_dscf5698.jpg)
This latest survey is routine and carried out every six years
National Highways contractors scaled the equivalent of four miles (six km) while the pictures were captured.
The bridge spans the Orwell Estuary and was constructed between 1979 and 1982.
![Picture looks down on a workman abseiling high above the ground, suspended from the bridge.](https://ichef.bbci.co.uk/ace/standard/976/cpsprodpb/9CB7/production/_131291104_bridge3.jpg)
Abseilers scaled the equivalent of four miles to complete the survey
The main arch is 190m (623ft) long, which, at the time of its construction, was the largest of its kind in use, external.
It rests on 40m (131ft) of pilings into the river bottom and is 43m (141ft) tall.
![Photograph from a distance of the entire Orwell Bridge.](https://ichef.bbci.co.uk/ace/standard/976/cpsprodpb/9A0F/production/_131293493_2ed9f155-6bc9-4beb-a7e2-acc59f659586.jpg)
At time of construction, the bridge was the longest of its kind in use
Work on the survey began in August, during most of which the bridge did not need to be closed, avoiding any disruption.
The final phase took place overnight for two weeks, where one carriageway was closed at a time, and was completed in the early hours of Saturday.
![A photograph looking up at one of the pillars, with two contractors abseiling.](https://ichef.bbci.co.uk/ace/standard/976/cpsprodpb/17F47/production/_131291189_bridge4.jpg)
The survey was originally pushed back to avoid disturbing nesting falcons, who had made their home on the bridge earlier in the year
![presentational grey line](https://ichef.bbci.co.uk/ace/standard/624/cpsprodpb/17BE/production/_92787060_line2.gif)
Follow East of England news on Facebook, external, Instagram, external and X, external. Got a story? Email eastofenglandnews@bbc.co.uk, external or WhatsApp us on 0800 169 1830
Related topics
- Published25 October 2019