Stadium for Cornwall: Cornish Pirates & Truro City ground work delayed until 2018
- Published
Work on the Stadium for Cornwall, to be shared by Cornish Pirates and Truro City, will not start any earlier than spring 2018.
A statement from Championship rugby side Pirates says they hope the ground will open in September 2019.
In December, club director Colin Groves estimated construction would begin "in the middle" of this year.
National League South side Truro only agreed to share the proposed 6,000-capacity ground with Pirates in April.
The statement said building will "hopefully" start next spring, with work on the stadium on the outskirts of Truro taking 14 months.
Stadium timeline
May 2010: Cornwall Council launch feasibility study into ground
May 2012: Councillors vote against public funding
January 2014: Developers say supermarket would fund stadium
April 2015: Truro City submit plans for rival ground
July 2015: PM David Cameron lends support as planning permission given
December 2016: Pirates director estimates work will start "in middle of 2017"
March 2017: Truro chairman told their ground is not viable
April 2017: Truro and Pirates set to share Stadium for Cornwall
May 2017: Work delayed until spring 2018
- Published13 April 2017
- Published11 April 2017
- Published6 December 2016
- Published13 May 2016
- Published3 February 2017
- Published15 February 2019